ABSTRACT
After detailed study on machines and levers, the construction work started as follows:-
Making out, pattern development, cutting filling, drilling, machining, assembling, welding and finishing. Detailed procedures carried out is located at the sequence of operation in subsequent pages.
The machine has scale of 1:5 in all parts of its dimensions. However, brief dimensions are given below:-
Upper surface of bowl - 850mm
Inner surface of bowl - 335mm
Stand height - 325mm
Diameter of wheel - 250mm
Diameter of shaft seating and the shaft 4mm
Thickness of type - 75mm
The drawing of the project was done and enclosed at the end page of this booklet. At last, a 150kg capacity of conveying machine was constructed.
TABLE OF CONTENTS
Title pages
Title page
Approval page
Dedication page
Acknowledgment page
Abstract
CHAPTER ONE
Introduction
Historical background
1.2 Need for constructing the machine
CHAPTER TWO
THEORY/LITERATURE SURVEY
2.1 Types of load to be carried by the conveyor
2.2 Operation of the wheel-barrow
CHAPTER THREE
3.1 Equipments/tools employed during construction of the wheel-barrow
3.2 Materials of construction
3.3 Construction procedure
3.4 Sequence of operation
3.5 Design calculations
3.6 Calculations basic on the bowl
3.7 Specifications
3.8 Project drawing
CHAPTER FOUR
COSTING OF PORTABLE WHEEL-BARROW
4.1 Material cost analysis
4.2 Labour cost analysis
4.3 Miscellaneous costs
Total cost
CHAPTER FIVE
5.1 Discussion
5.2 Precautions taken during construction
5.3 Cautions to users
5.4 Recommendations
5.5 Conclusions
References
Disclaimer: Note this academic material is intended as a guide for your academic research work. Do not copy word for word. Note: For Computer or Programming related works, some works might not contain source codes
CITE THIS WORK
(2014, 12). Construction Of Portable Wheel-barrow.. ProjectStoc.com. Retrieved 12, 2014, from https://projectstoc.com/read/5521/construction-of-portable-wheel-barrow-5809
"Construction Of Portable Wheel-barrow." ProjectStoc.com. 12 2014. 2014. 12 2014 <https://projectstoc.com/read/5521/construction-of-portable-wheel-barrow-5809>.
"Construction Of Portable Wheel-barrow.." ProjectStoc.com. ProjectStoc.com, 12 2014. Web. 12 2014. <https://projectstoc.com/read/5521/construction-of-portable-wheel-barrow-5809>.
"Construction Of Portable Wheel-barrow.." ProjectStoc.com. 12, 2014. Accessed 12, 2014. https://projectstoc.com/read/5521/construction-of-portable-wheel-barrow-5809.
- Related Works
- Industrial Pollution And Green House Effect
- Construction Of Water Storage Tank (2000 Litres)
- Effect Of Interface On The Quality Of Petroleum Product In Multi Purpose Pipeline System
- Modification Of Surface, Physical And Chemical Properties Of Activated Carbons For Water Purification
- Construction Of A Stell Cupboard
- Production Of Wood Adhesive
- Design The Absorber (scrubber) In The Process Plant For The Production Of 100,000 Metric Tonnes/ Year Of Ethanol From Direct Hydration Of Ethylene
- Desulphurisation Of Kerosene
- Water Pollution
- The Construction Of Sieve Equipment